This picture shows the hallway where the new SW entrance will be located after the building addition is completed. All of the classrooms on the lower level have the concrete poured for the floor. The steel is also in place for the ceiling of the lower level.
On November 19, crews continued their work on placing steel on the second floor to support the new roof. The next steps include finishing the steel for the roof, enclosing the new windows and doors and making preparations for pouring the concrete floors for the 2nd floor classrooms.