All of the tile flooring has been installed throughout the addition. Tile flooring is being used in each room as well as the bathrooms. The classrooms for our younger students downstairs have more tile than carpet. You can see from the picture that different colors of tile have been used to create a pattern.
Terrazzo flooring is being poured in the entries to each classroom and in the hallway on the 2nd floor. The picture on the left shows half of the terrazzo poured in the hallway upstairs.
Where CHARACTER COUNTS!
Tuesday, May 3, 2011
Friday, April 8, 2011
Book Fair Fun!
As you can see from the pictures, I was "silly-stringed" for meeting our goal at the Book Fair. Our goal was to have our total sales reach $8,000. With everyone's help, our total sales reached almost $10,000. Thank you to everyone who participated in this year's book fair! A BIG thank you to our parents who volunteered throughout the book fair to make it so successful!
Monday, April 4, 2011
Progress Continues on the Addition
The ceiling grid and lights are in place on the 2nd floor and are currently being installed on the 1st floor. Ceiling tiles will be installed once the work above the ceiling is completed. Larson Contracting is also installing cabinets, countertops and cubbies in each room throughout the addition.
Friday, March 18, 2011
Hanging the Ceiling and the Cabinets Come Next!
Cabinets and cubbies were delivered this week for all of the classrooms in the new addition. As painting was finished up this week in the classrooms, they will begin to hang the ceiling grid next week. These rooms will begin to look more like classrooms in the coming weeks!
Friday, March 11, 2011
Primering and Painting
Shaw's of Okoboji has completed one week of primering and painting and will plan to finish up next week. The crew started the week painting all of the door frames a maroon color to match the existing building door frames. The crew then moved on to primering the new concrete block before painting the new walls a beige color.
Thursday, March 3, 2011
You Can Clearly See the Progress
The windows have been installed in the 2nd floor classrooms and they have started installing the windows on the lower level as well. Shaw's of Okoboji will begin primering and painting the concrete block walls of the addition next week.
Saturday, February 26, 2011
FFA Week February 20-26
Elementary students participated in a coloring contest in recognition of FFA week. Thank you to Rich Martin, FFA advisor, and his students for including the elementary students in their week of activities.